Dairylain Farms

Dairylain Farms

Sunday, July 24, 2011

Construction update

We are at the end of week 4 of construction. We have gained a  lot of concrete in 4 weeks. The lanes at the ends are left to pour as well as the feed alleys and alley to move the cows to the barn. Work was a little slower this week as the crew was in Hampton installing a hay barn. These pics should give you a good idea of how everything will be connected together.





This doe was getting breakfast the other morning from the bag of corn.
These killdear hatched in the driveway. One of the three is still wet. The fourth egg hatched the following day and we were lucky to get a picture as they took them all away soon after they hatched.

No comments:

Post a Comment