Construction update

We are at the end of week 4 of construction. We have gained a  lot of concrete in 4 weeks. The lanes at the ends are left to pour as well as the feed alleys and alley to move the cows to the barn. Work was a little slower this week as the crew was in Hampton installing a hay barn. These pics should give you a good idea of how everything will be connected together.





This doe was getting breakfast the other morning from the bag of corn.
These killdear hatched in the driveway. One of the three is still wet. The fourth egg hatched the following day and we were lucky to get a picture as they took them all away soon after they hatched.

Wednesday, July 6, 2011

Starting Construction

Construction finally got underway on June 28. The crew seems to be wasting no time after a day and a half the concrete truck was here and things were starting to take shape. They have the 2 outer alleys poured, 2 curbings, 1 manger curb and have moved and piped the water line.